Xpeng signs deal to build NeoPark equivalent in Zhaoqing
Xpeng CEO said the company expects to see the industrial park bring in 80 to 100 companies from the supply chain in the next 2 to 3 years.
The project started on March 28, 2021 and took 6 months to complete the topping out of the 500,000 square meter plant and saw the first equipment installed on site within 8 months.
Ten months after the project began, the first battery pack samples rolled off the production line and production started 14 months after the start of construction, a press release from the Zhaoqing government said.
Based on the two projects, Xpeng as well as CATL, the Zhaoqing municipal government has planned the construction of the 45-square-kilometer Dawang New Energy Intelligent Vehicle Industrial City, which will be turned into a national-level new energy intelligent vehicle industrial city, according to the press release.